How Long Does a DA Take in New South Wales?
Your Guide to Approval Timelines That Can Make or Break Your Project
Let’s get real — in development, time is leverage. And if you don’t know how long your Development Application (DA) could take in NSW, you’re flying blind.
Whether you’re building your next investment, renovating, or unlocking value in your land, knowing how the system works — and where delays can happen — helps you move faster, smarter, and with fewer surprises.
Standard DA Approvals in NSW: What You’re Really Working With
For most straightforward projects, your DA approval should take 40 days. But let’s not sugar-coat it — that’s the ideal scenario.
Here’s what can push timelines out:
Want to move faster?
Integrated Development Applications (IDAs): When It Gets Complicated
If your project needs approvals from multiple government agencies, you’re in integrated development territory.
Think of it as a one-application, many-decision-makers scenario.
That might include:
And here’s the truth:
The more agencies involved, the longer it takes.
The assessment period is 60 days for a development application—
Timeline Range:
If your development impacts the community, environment, or heritage — plan accordingly. Your patience and prep work will get tested.
State Significant Development Applications
The assessment period is 90 days for a development application (if additional information is not requested) —
Timeline Range:
Real Projects. Real Timelines. Real Lessons.
Here’s what actually happens on the ground in NSW:
Example: Standard DA – Single Dwelling in Sydney
Example: Integrated DA – Commercial Mixed-Use Development
These examples show what you’re really dealing with — and why preparation is your best insurance.
Bottom Line: Knowledge = Control
Navigating DA approvals in NSW doesn’t have to be overwhelming — but it does have to be strategic.
If you want to avoid months of delays, missed milestones, and cash burn, you need to:
The Winning Formula
In this game, success comes down to People. Product. Process.
That’s how you cut through the noise and get approved faster.